Labour Usage - Fitting Percentages

A more general way of applying fittings is to use the Fittings Percentages form. As with the usage fittings, when the labour usage is applied to an estimate item, the values are added automatically. These can then be edited as necessary.

To apply the usage fittings on loading a labour usage, the Apply Fittings option on the Estimate Details tab must be set to Yes.

See Add a fitting to a steel item.

The columns on the Fittings Percentage form are described in the following table.

Column

Description

Up To Length

Enter a length.

This is the upper limit to which the settings apply. If the item exceeds this length, it is ignored.

Fittings %

Specify the weight of the fitting as a percentage of the parent bar, for example the required fittings may be an additional 10% of the parent bar.

Rate Per (<unit of weight>)

Specify the price of the material required for the fitting, for example, GBP 250.00 per tonne.

Hour Per (<unit of weight>)

Specify the number of hours required to add the fitting(s), for example, GBP 2hrs per tonne.